Fort Wayne to Consider Riverfront Contracts
Subscriber Benefit
As a subscriber you can listen to articles at work, in the car, or while you work out. Subscribe NowFort Wayne Mayor Tom Henry says more than $17 million in construction contracts for the first phase of the Riverfront Fort Wayne project are ready for approval. The contracts will be presented to the Fort Wayne City Council and the Board of Park Commissioners next week.
To date, nearly $20 million has been committed to the project, including $10 million in Legacy funding for construction, more than $5 million in Regional Cities Initiative funding and $4.8 million in private donations. Fort Wayne Parks & Recreation Director Al Moll says the city is looking forward to getting construction underway.
"Our community and region have embraced this initiative and the possibilities that exist by developing our rivers," said Moll. "The financial support we’ve received from public and private entities helps ensure riverfront development will be a world-class experience for everyone involved."
The first phase of Riverfront Fort Wayne will focus on public spaces in a park setting, according to the city. Plans include a promenade, park pavilion, and an event lawn, among other amenities.
The construction contracts will be introduced to the city council May 9 with a preliminary vote possible on May 16. Final passage could occur May 23. The mayor’s office says the Board of Park Commissioners could vote to approve the contracts May 11.
The contracts include:
- Demolition, Excavation and Site Work – Crosby Excavating, $2,321,190
- Landscaping – Dave Harlow Enterprises, $2,498,906
- Concrete Dock Walls and Tree Canopy Trail – Kenny Construction Company, $3,069,000
- Site Concrete – Hamilton Hunter Builders, $1,780,629
- Masonry – Hamilton Hunter Builders, $218,109
- Structural Steel Fabrication – Almet, Inc., $1,966,000
- Miscellaneous and Structural Steel Erection – Don Fruchey, Inc., $220,500
- General Trades – Fetters Construction, $1,290,000
- Roofing – C.L. Schust, $155,000
- Aluminum Storefront and Glazing – Hall Aluminum Products, $327,000
- Finishes – Rosema Corporation, $251,000
- Fire Protection – VFP Fire Systems, $49,947
- Mechanical – Project Design and Piping, $863,000
- Electrical – Hambrock Electrical, $1,385,500
- Trailhead Restroom, $208,662
- Harrison Street Asphalt Paving – Crosby Excavating, $58,190
- Playground Equipment and Surfacing, $200,000
- Site Specific General Conditions, $592,251
In March, the Board of Park Commissioners closed on the final three properties that make up the first phase of the $20 million project. Construction on the project is expected to begin in July and take 18 months to complete.
You can learn more about the Riverfront Fort Wayne project by clicking here.